Phase III: Schedule for Completed Spaces


Fall 2000

  • East passenger elevators
  • Stacks 7 & 8

Spring 2001 - Fourth Floor

  • Periodicals & Microforms Reading Room

Summer 2001 - Fourth Floor

  • Balance of Philip L. Milstein Family College Library Reading Rooms

Fall 2001 - Fifth Floor

  • 5th Floor Offices & Meeting Rooms
  • Stacks 9 & 10
  • West passenger elevator

Summer 2002 - Fifth Floor

  • Electronic Publishing Initiative at Columbia (EPIC)
  • Columbia Center for New Media Teaching & Learning (CCNMTL)

Fall 2002 - Fifth Floor

  • Research Reading Rooms (3)
  • Stack 11

Spring 2003 - Sixth Floor

  • RBML Workroom & locker room
  • New Stairs to 7th floor post M-Phil research space (E & W)

Summer 2003 - Sixth Floor

  • Research Reading Rooms (5)